Project data, communication, planning and execution in one place.

Qlira holds the project as one live record built from your schedule, feeds it with what the field reports every day, and replans after each change. The people on the project get a workspace for their role. The project manager gets the forecast and the decisions.

The daily workflow

Four steps, every day, most of them without a meeting.

KT2·Documents · KT2 BL R3 13-02-27.xer

Activities

1,093

Matched

1,041

New

43

Needs a look

9

In the fileTask
A1240L12 SLAB POUR ZONE A+BSTR-1240
A1188L11 COLUMNS GL A-FSTR-1188
A1305L13 COLUMNS (REV)STR-1301
A2117CHW RISERS L10-14 DELIVERYNew task
A0742CABLE CONTAINMENT L9MEP-0742

Apply as baseline “BL R3 · 13 Feb”. Progress the site has reported is never overwritten.

Bring the project in

Import the schedule from the tool you plan in. Activities are matched to existing tasks; you review only the rows that need a human. The next revision comes in the same way, without losing what the field reported.

07:42Today · Kestrel Tower 2 · Zone B
Daily report
draft

6 tasks today

4 of 6 saved · 1 done · 3 in progress
Plan for Mon 15 Feb
issued

5 tasks received · review quantities

Submit before end of shift
Pending work

2 tasks carried over

Oldest pending 3 days
07:42Daily report · 14 Feb
STR-1240 Level 12 slab pourin progress
12%

Crew 14 · 2 pumps · Pour zone A done, zone B formwork 60%

STR-1188 Level 11 columnspaused
78%

Crew 6 · Rebar C to E on hold, shop drawing

FIN-0410 Blockwork L8in progress
30%

Crew 9

FIN-0322 Screed L7completed
100%

Crew 4

Updates from the people doing the work

Status, progress, crew, quality, a photo, a remark, per task, from a phone. Engineers review with a cause tag. Blockers route to whoever can clear them.

KT2·Assessing the project

Assessing the project

The engine rebuilds the forecast from the live schedule and every report since the last run.

  1. Snapshot1,093 tasks, their links, calendars, daily reports, permits and open deliveries as of today.
  2. Work calendarsWorking days, hours and holidays per task, so durations count site time.
  3. Critical pathForward and backward pass over FS / SS / FF / SF links: early and late dates, float, the critical chain.
  4. Learned durationsHow long this company's activities really take, from its finished work; reported pace overrides it.
  5. Finish simulation300 runs of the remaining work: the likely finish, its range and the chance of a late one.
  6. Risk checks13 checks: pace, float, readiness, blockers, stale reports, permits, supply, forecast. Each with its evidence.
  7. RecommendationsCandidate actions scored by their what-if gain on the finish date.
  8. Write-backDates, float and criticality onto every task, and an event on the log.

Done in 14.8 s. 7 risks flagged, 4 recommendations, forecast +6.5 d against the plan.

Qlira AI replans

After every update: critical path, forecast, risk checks, actions scored by the days they recover, and the work ahead rescheduled. Automatic, and on demand.

KT2·Today · recommendations

What Qlira recommends

4 actions · up to 8.0 d recoverable

1Add crew+3.5d
STR-1240

Second formwork crew on Level 12 slab from Monday

Why?
2Expedite material+2.0d
MEP-0880

Chase PO-0417 chilled-water risers, due 21 Feb, supplier 62% on time

Why?
3Re-sequence+1.5d
FIN-0410

Start Level 8 blockwork before Level 9 screed; no float lost

Why?
4Escalate+1.0d
STR-1188

Column rebar hold: shop drawing approval 11 days overdue with the consultant

Why?

Decide, on the record

The ranked actions sit next to the forecast on the project manager’s Today. Accept, dismiss or ask why. Each decision is an event on the project’s log.

07:42Today · Kestrel Tower 2 · Zone B
Daily report
draft

6 tasks today

4 of 6 saved · 1 done · 3 in progress
Plan for Mon 15 Feb
issued

5 tasks received · review quantities

Submit before end of shift
Pending work

2 tasks carried over

Oldest pending 3 days

Tomorrow’s plan

The AI drafts each crew’s next day. The engineer issues it, the supervisor adjusts with a reason, the engineer approves. Nobody chases anyone.

KT2·Today · look-ahead

On the horizon

What starts and finishes next, on the dates the engine forecasts.

Next 3 days

14 – 17 Feb

1 starting · 2 finishing · 1 critical · 1 behind

STR-1188Level 11 columnsFinishes 18 Feb+6 d vs planbehindcritical
MEP-0742Cable containment L9Finishes 17 Feb
FIN-0455Blockwork L9Starts 16 Feb

Next 3 weeks

17 Feb – 7 Mar

3 starting · 2 finishing · 2 critical

MEP-0880Chilled water risers L10 to L14Starts 22 Feb
STR-1240Level 12 slab pourFinishes 4 Mar+6 d vs plancritical
STR-1301Level 13 columnsStarts 1 Marcritical

Next 3 months

7 Mar – 16 May

14 starting · 11 finishing · 2 milestones · 4 critical

STR-M04Structure to L15Milestone 9 Apr+6 d vs plancritical
MEP-M02Chillers energisedMilestone 30 Apr

The road ahead

Three days, three weeks, three months of starts, finishes and milestones on forecast dates, with critical and behind marked.

KT2·Today

Forecast

Slipping, inside tolerance

Finish

1 Aug 2027

Slip

+6.5 d

P(late)

38%

Done

41%

Planned

46%

SPI

0.89

Open risks

7

2 high4 medium1 low

Assessed

07:41

14 Feb, after 3 site reports

One workspace per role.

Project manager
Forecast, risks, ranked actions, KPIs, report-outs. Decides on recommendations and escalations.
Planner
Imports, baselines, the live plan with critical path and forecast, dependency editing.
Site engineer
Supervisors’ updates to review, plans to issue and approve, blockers assigned to them.
Site supervisor
Daily update, tomorrow’s plan, pending work. Three taps from the phone’s home screen.
Safety officer
Permits to verify, daily duties, observations, incidents, training, HSE report-outs.
Procurement
Requisitions, quotes, purchase orders, deliveries, supplier reliability.
Accounting
Cost lines, ledger, applications and variations, petty cash, month close.

Bring the project from wherever it lives.

Schedules, reports, spreadsheets and messages come in as they are. Nothing to re-key, and the planner keeps working in the tool they know. Greyed sources are on the way.

  • Primavera P6

    .xer · .xml · PDF

  • Microsoft Project

    .mpp · .xml

  • Excel

    .xlsx · .csv

  • Google Sheets

    shared sheet

  • PDF reports

    progress, minutes

  • Word

    .docx

  • Email

    forwarded updates

  • WhatsApp

    coming

  • Asta Powerproject

    coming

  • Procore

    coming

  • Autodesk Construction Cloud

    coming

  • Aconex

    coming

  • Microsoft Teams

    coming

  • Slack

    coming

  • Power BI

    coming

  • SAP

    coming

Start with one project.

Tell us about your projects and the tools you plan in. We set your team up, bring in a schedule and walk you through the first assessment together.